January Work Progress
Week of Feb. 7th
Monday was spent putting the siding on the chimney.
Tuesday and Wednesday was supposed to rain so
we took a couple of days off.
Thursday was cold and windy so installing
the window and corner trim was done.
Friday was spent cutting the shingles
and installing the flashing to the new tin roof.