Week of March 21st

A lot of work done this week with the
second set of French Doors being installed
and all the electrical, phone and cable wires
being roughed in.

Step from the Florida Room to the Office is completed
by DJ so now ready to install the 15 light door.

Sheetrock started in the office North wall.

Electric boxes installed for the track lighting and
speakers to be used on the surround sound.

On Monday, March 28th DJ finished the wiring and we
hooked up the 8/3 100 foot wire to the main box. Power
now up and perfect to the new addition.

Last door, the 15 light between the two rooms is installed.